Building envelope manufacturer and contractor CA Group has praised the support it received from gearbox specialist Apex Dynamics UK to redesign the gearbox specifications in its converting machine, delivering much greater flexibility and dramatically cutting maintenance downtime. CA Group has been creating and delivering advanced build systems to developers for more than 30 years and its products feature on hundreds of buildings across Europe.
The company has a converting machine for the manufacture of steel sections for cladding containing a series of 20 Apex Dynamics spiral bevel gearboxes working together. CA Group’s maintenance team identified a problem with the previous set-up, as the gearboxes were connected by a solid shaft all the way through, which did not allow for any flexibility of movement.
This flaw in the overall design meant that seals were under strain and often began to leak, leading to high failure rates. Additionally, if a gearbox failed or a seal blew out, it would result in 5-6 hours of downtime to repair the machine because of the difficulty of accessing the gearboxes in order to change them.
Apex Dynamics UK and CA Group worked together to find the ideal solution

A new platform for the gearboxes to sit on has also been created for the converting machine by Apex Dynamics UK and CA Group that reduces downtime in the event of a gearbox failure. The base of the machine is no longer one solid piece and so, rather than having to dismantle elements of the machine in order to change gearboxes, the platform can simply slide in and out to change gearboxes within 20-30 minutes, compared with 5-6 hours previously.
New design slashes downtime and improves performance

Stuart Lowe, CA Group Works Engineering Manager, comments, “We really appreciate the support provided by the knowledgeable expert team at Apex Dynamics. Having identified the problem, this was a truly collaborative project that resulted in the right solution to provide the flexibility needed and ensure our converting machine runs smoothly.”
Phil Waldock, CA Group Maintenance Supervisor, adds, “We are really happy with the solution from Apex Dynamics UK. Since the design has been changed over, there has not been a single gearbox fail or seal blow out.”
Apex Dynamics UK Northern Area Manager, Malcolm Hillary, who worked closely with CA Group on the project, comments, “We were very pleased to be able to help CA Group find the correct solution. They came to us with issues surrounding gearboxes leaking and we confirmed their analysis of the problem. Working in partnership, we were able to successfully solve the issues of non-flexibility between the gearboxes and make the converting machine easier to maintain in the future.”

Company : CA Group